Text size: A A A
Home
   RIIO ED1 Revised Business Plan
     Main Business Plan Documents and Annexes

     RIIO-ED1 Commitment Report

     All Asset Management Documents
       Volume Justification
          EPN Justification Documents
          LPN Justification Documents
          SPN Justification Documents
       High Value Projects Justification
       Regional Development Plans
          EPN RDP Justification Documents
          LPN RDP Justification Documents
          SPN RDP Justification Documents

     Cost Justification and Assurance Documents

     Stakeholder Engagement Supporting Documents

     Ofgem RIGs Data Tables

   Connections quotation
     Customer responsibilities
       3.1 On-site trenches and cable route
       3.2 Ducts
       3.3 Services to houses
       3.4 Services to flats
       3.5 Building Network Operator (BNO) responsibilities
       3.6 Unmetered connections
       3.7 Temporary builder's connections
       3.8 Landlord's connections
       3.9 Commercial or industrial connections (400Amps and below)
       3.10 Commercial or industrial connections - CT metering large low voltage connections (more than 400Amps)
       3.11 Substations: associated with LV connections
       3.12 Substations associated with HV and EHV connections
       3.13 Substations: primary sites
       3.14 Substations: grid sites
       3.15 G59 witness testing
       3.16 Primary/grid transformer
       3.17 Power Factor
       3.18 Active Network Management (ANM) local control requirements for the Flexible Distributed Generation (FDG) quote
       3.19 Land rights (time to complete the legal work between Your solicitors and UK Power Networks’ solicitors)
       3.20 Land rights required from You (freehold/leasehold of the substation site)
       3.21 Land rights required from You (easements for the underground cables)
       3.22 Land rights required from You within its occupation, ownership or control (termed wayleave for the underground cables)
       3.23 Land rights required from others (property outside the actual site boundary)
       3.24 Land rights required from others (agreement in principal from the relevant landowner)
       3.25 Construction (Design & Management) Regulations (CDM) 2015
       3.26 Appoint an Electricity Supplier
       3.27 Works to be undertaken by the ICP/IDNO if UK Power Networks is undertaking the non-contestable Works only
       3.28 Land rights for option B or C - where UK Power Networks is undertaking the non-contestable Works only
       3.29 Quicker and More Efficient Connections – Queue Management and Connection Milestones

     Information to help you plan your works
       4.1 Information common to all quotes
          4.1.1 About our network
          4.1.2 Safety
          4.1.3 Matrix of technical information associated with the Works
          4.1.4 Prospective Short Circuit Current (PSCC)
          4.1.5 The Point of Supply
          4.1.6 Supply disturbances
          4.1.7 Guaranteed Standards of Performance (GSoP)
          4.1.8 Standard leaflets and fact sheets
          4.1.9 Contact us
          4.1.10 Lane rental charges
          4.1.11 Programming your work
          4.1.12 Appointing an ICP or IDNO
          4.1.13 Assets to be adopted by UK Power Networks
          4.1.14 Cable identification by ICPs and IDNOs
          4.1.15 Pre and post-connection tests for Low Voltage contestable works
          4.1.16 Pre and post-connection tests for High Voltage contestable works
          4.1.17 Engineering recommendations G81
          4.1.18 Parent Company Guarantee Bank Guarantee Form
       4.2 Supply characteristics at the Point of Supply for LV Metered and Un-metered customers
       4.3 Supply characteristics for HV and EHV Points of Supply
       4.4 Earth Fault Loop Impedance (EFLI)
       4.5 Cables between UK Power Networks and Your installations up to 400Amps
       4.6 Private generation
       4.7 Second Comer Electricity (Connection Charges) Regulations 2002 and 2017
       4.8 Basis of Curtailment under the Connection Agreement
       4.9 Abnormal network conditions
       4.10 Interactive process
       4.11 Conditional interactivity applies
       4.12 Unconditional interactivity applies
       4.13 The Voltage Rule

   EnvReports201617
   G81 Documents
     Materials Specification
       Cables
          Documents
          Drawings
       Earthing
          Documents
          Drawings
       General
          Documents
          Drawings
       Network Operations
          Documents
          Drawings
       Overhead Lines
          Documents
          Drawings
       Planning & Design
          Documents
          Drawings
       Protection & Control
          Documents
          Drawings
       Switchgear
          Documents
          Drawings
       Substations
          Documents
          Drawings
       Transformers
          Documents
          Drawings

     Design & Planning
       Cables
          Documents
          Drawings
       Earthing
          Documents
          Drawings
       General
          Documents
          Drawings
       Network Operations
          Documents
          Drawings
       Overhead Lines
          Documents
          Drawings
       Planning & Design
          Documents
          Drawings
       Protection & Control
          Documents
          Drawings
       Switchgear
          Documents
          Drawings
       Substations
          Documents
          Drawings
       Transformers
          Documents
          Drawings

     Installation & Records
       Cables
          Documents
          Drawings
       Earthing
          Documents
          Drawings
       General
          Documents
          Drawings
       Network Operations
          Documents
          Drawings
       Overhead Lines
          Documents
          Drawings
       Planning & Design
          Documents
          Drawings
       Protection & Control
          Documents
          Drawings
       Switchgear
          Documents
          Drawings
       Substations
          Documents
          Drawings
       Transformers
          Documents
          Drawings

     Testing & Commissioning
       General
       Grid & Primary
       Secondary
       Miscellaneous

     Authorisation and Training

     Documents for Review

   g81
     Index

     Alerts and Bulletins

     Design and Planning
       General
       LV
       HV
       EHV
       Substations
       Substations (Secondary)
          General
          Brick-built
          Integral
          Basement
          Other
          GRP
       Substations (Customer)
       Substations (Major)
          General
          Elevated
          Enclosed
          Grid
          Primary
       Earthing
       Smart Grid
       Cables
       Overhead Lines
       Switchgear
       Transformers
       Protection and Control
          Schemes
          11kV Drawings
          SCADA
          132kV Drawings
          33kV Drawings
          AVC
          Protection Settings

     Materials

     Installation
       Substations
       Earthing
       Cables
       Overhead Lines
       Switchgear
       Transformers
       SCADA

     Testing and Commissioning
       General
       Secondary
       Grid and Primary

     Operational
       Distribution Safety Rules
       Authorisation and Training
       Switching
       Access
       Testing
       Cables
       Overhead Lines
       Transformers
       Protection
       LV
       Audit

     Records

     Legal

     ICP

     Reference

     Documents for Review