Please remember that we will not be able to programme any work until all of the following have been carried out:
We have received any requested payment and a signed Acceptance Form
All necessary legal consents have been completed successfully
A site meeting has taken place with our Delivery Team to determine the scale and complexity of the works (if we believe this is necessary).
If You are accepting option B or C, then we must have reviewed and accepted the design and programme for the ICP or IDNO Works.