3.27 Works to be undertaken by the ICP/IDNO if UK Power Networks is undertaking the non-contestable works only

If You select option B or option C of Your Quote, the ICP/IDNO appointed by You will need to complete the following where applicable:

  • Liaise with the CiC Delivery team before starting work. 

  • Design of network extension to include as a minimum the information shown on our website.

  • Conduct studies and demonstrate compliance with Engineering Recommendations P28, P29, G5/5 and G99 as appropriate.

  • Ensure that any harmonics produced which are transmitted onto the Distribution System are within the limits stated in ENA EREC G5/5.

  • Legal acquisition of cable easements and substations on UK Power Networks' standard documentation without amendments.

  • Obtain design acceptance of the Contestable Works from UK Power Networks.

  • Planning permission for any substations with an aerial.

  • Supply of all materials required for the Contestable Works.

  • Excavation, cable laying and reinstatement of cable route between the points of connection and points of isolation.

  • Break open any UK Power Networks ducts as necessary.

  • Carry out excavation to the base of the overhead line pole with the final metre of excavation/reinstatement being observed by UK Power Networks.

  • Construction of substations, including earthing, power and lighting.

  • Installation of substation equipment - RMU with automation on both ring switches.

  • Cable and substation jointing and fitting.

  • Joint bays, excavation & permanent reinstatement for cable identification and final connections.

  • NRSWA compliance including for final connections.

  • Obtain opening notices and permits.

  • Project Management, operational safety, regulation compliance and testing.

  • Submission to the company of as laid drawings and test results.

  • To obtain and provide copies of any required environmental licences or permits.

  • Supply and installation of a suitable RTU including power.

  • Obtain sign-off of the substation civil works prior to the delivery of the plant. 

  • Construction of pillars, including earthing - additional earthing ring if metallic. 

  • Cable jointing. 

V2_April2024