If You select option B or option C of their Quote, the ICP/IDNO appointed by You will need to complete the following where applicable:
Liaise with the CiC Delivery Manager before starting work
It is Your/ICP/IDNO's responsibility, where applicable, to conduct a worst case scenario generation study to ensure compliance with G59/1, G59/3 or G83 as appropriate. This study is to include the effect on UK Power Networks’ network in the Design Submission. The results are to include:
The fault level contribution
The step change in voltage
Confirmation whether or not the generation will export onto the DNO network (export profile)
UK Power Networks will then advise You whether the generation can be connected at the proposed Point of Connection (POC) or if a new POC is required.
Legal acquisition of cable easements and substations on UK Power Networks' standard documentation without amendments
Planning permission for any substations with an aerial
Supply of all materials required for the ICP/IDNO Works
Break open any UK Power Networks ducts as necessary
Construction of substations, including earthing, power and lighting
Installation of substation equipment
Cable and substation jointing and fitting
Joint bays, excavation & permanent reinstatement for cable identification and final connections
NRSWA compliance including for final connections
Obtain opening notices and permits
Project Management, operational safety, Regulation compliance, testing etc.
Submission to the company of as laid drawings and test results
To obtain and provide copies of any required Environmental licences or permits
Supply and installation of an RTU approved by UK Power Networks, including its power supply. Click HERE to see specifications of approved RTUs
Obtain sign off of the substation civil works prior to the delivery of the plant
Construction of pillars, including earthing - Additional earthing ring if metallic
Supply and Installation of cut out, fuse carriers, specified fuses and CT's
Cable jointing
Joint bay excavation & permanent reinstatement for cable identification and final connections
V1_December2015