The proposal plan provided with your Quote indicates which of the following You are responsible for:
GRP housing
Ensuring that 24-hour unimpeded access is available for UK Power Networks staff and its contractors throughout the year.
GRP plinth
Or
Brick built substation
The specification for the necessary civil works, along with the associated earthing. These details are indicated on the drawing provided with your Quote.
Ensuring that 24-hour unimpeded access is available for UK Power Networks staff and its contractors throughout the year.
Or
Integrated substation
The accommodation is to be available to UK Power Networks with adequate access at least 4 weeks prior to commencement of UK Power Networks' work.
You must test the installation on completion and provide a test certificate to the UK Power Networks Field Engineer dealing with the site.
The provision of a suitable plinth and associated civil works to accommodate the substation located as shown on the proposal plan provided with your Quote.
Ensuring that 24-hour unimpeded access is available for UK Power Networks staff and its contractors throughout the year.
Delivery of plant
Please note that plant can only be delivered to site when a suitable hard standing surface is available.
Substation civil wokrs
Energisation