3.21 Land rights required from You (easements for the underground cables) 

UK Power Networks will require easements, in perpetuity, for the underground cables along the routes marked on the plan provided with your Quote.

These cable easements will require a restriction upon the planting of trees and erection of structures, other than such as already exist or are shown proposed on the said plan, on or within 2.0 metres of the centre line on the land highlighted in the plan. This should be taken into account when carrying out the Your landscaping proposal.

 You are advised against disposing of your interest in any part of the development which might be subject to the easement before the same has been noted at Land Registry, as UK Power Networks will not bear any additional legal costs which might arise should this requirement be disregarded.

 

V1_December2015