3.20 Land rights required from You (freehold/leasehold of the substation site) 

The work requires the freehold/leasehold of the substation site as indicated on the drawings provided with your Quote; access and cable rights and easements to be transferred to UK Power Networks for the nominal sum of £1.00, with each party bearing its own legal costs.

If the method of supply requires a UK Power Networks' Supply substation, You will need to ensure that UK Power Networks is provided with suitable accommodation on the relevant premises for UK Power Networks electric lines and apparatus to provide control and meter the supply. The accommodation must be available at all times provided and provided at no cost to UK Power Networks.  

Please remember that access to the UK Power Networks' substation is required at all times and maintenance to the UK Power Networks equipment may necessitate an interruption of the supply.

 

V1_December2015